Resource Capacity Planning 06-01-2017 Creator: Rick Nyarady

Home Forums OpenPPM Bulma 4.2.9 Resource Capacity Planning 06-01-2017 Creator: Rick Nyarady

  • This topic contains 1 voice and has 0 replies.
Viewing 1 post (of 1 total)
  • Author
    Posts
  • #3442

    TalaiaOpenPPM
    Participant

    When planning resources I want to make sure I do not exceed 100%. This is particularly important for PM assignments. I can visually see conflicts but I was wondering if their is a warning message if I exceed 100%?

     

    -Talaia (17-01-2017)

    Hi Rick,

    There are no warning message. You can visualize over-assignement with a different colour. Colors can be configurated in the general tab of the Admin Module.

     

     

     

Viewing 1 post (of 1 total)
  • You must be logged in to reply to this topic.