Anyone figure out how/when the workingcosts table is used?
What action triggers an insert into this table?
Søren
-Joan Barceló (13-09-2013)
Hi Søren,
workingcosts table is used in “Initiation” -> “Project Charter” -> “Direct Costs”
Kind Regards,
Joan